Project Update #7: Project Timeline

To date, the OCLS Redesign Team has determined the site navigation and layout of the homepage for the new website. The RFP was released to potential contractors for Drupal development.

The following is the projected timeline for the website redesign project:

  1. Request for proposal (RFP) goes out for developer - January 2015
  2. Design mock ups - January and February 2015
  3. Internal wireframe testing - January 2015
  4. Hire developer - February 2015
  5. Development begins - February/March 2015
  6. Quality Assurance - May 2015
  7. New site beta testing - May and June 2015
  8. Staff training - July and August 2015
  9. Soft launch of new site - September 2015
  10. New website launched - October 2015